  • November 5, 2026 at 3:56 pm in reply to: 1 (A). Sweeping Over-billing under the Rug 2 #36189
    Caleb Dobson
    Participant

      Based on this week’s reading the below suggestions are three specific recommendations that I would make to an owner who wishes to avoid this type of situation?

      1. Enforce Mandatory Invoice Verification Rules

      An owner should never pay an invoice based on trust alone. The contract must mandate that suppliers provide granular, verifiable proof of work before any payment is disbursed.

      To do this I would: Implement a “No Proof, No Pay” policy. Mandate that the accounting department reject any invoice that does not include an attached sheet listing exact room-by-room dimensions alongside signed post-installation photos.

      2. Conduct Routine Random Audits on Active Contracts

      Relying entirely on standard operational staff to spot over-billing is a major risk. An owner must introduce a secondary layer of financial accountability through periodic, unannounced audits.

      For this I would: Schedule a recurring quarterly spot-check. Calendar a mandatory review every three months where a manager randomly pulls 3 completed work orders, visits to measure, and verify the physical size against the billed amounts.

      3. Strictly Meet or Formally Amend Your Own Contractual Obligations

      If an owner fails to deliver on their operational promises, it opens the door for contractors to legally claim “breach of contract” or demand costly, unverified extras.

      To enforce this I would: Conduct a pre-start “Audit.” Before a contract goes live, have the project manager highlight every single item the owner promised to provide. If any item cannot be delivered, legally remove it from the agreement with a formal written amendment before work begins.

      November 5, 2026 at 3:45 pm in reply to: 2 (A). What Comes Out in the Wash? #36188
      Caleb Dobson
      Participant

        I agree, we all make mistakes so since the quantities changed the RFP was no longer correct in its orignal format, an amendment should have been posted to inform all vendors of the change so they could bid correctly or update their current submission.

        November 5, 2026 at 3:41 pm in reply to: 2 (A). What Comes Out in the Wash? #36187
        Caleb Dobson
        Participant

          Eric I think you’re on to something here. It is great they provided the revised number of washes however you’re right legally they should have made an amendment advising everyone that the number had changed and this would have prevented a lawsuit or at least presented a lot less confusion and probably cause for a lawsuit.

          November 5, 2026 at 3:33 pm in reply to: 2 (A). What Comes Out in the Wash? #36186
          Caleb Dobson
          Participant

            I agree Danny, “say what you’re going to do and then do what you said”. Very simply in theory, however with this example it appears to be a lot more confusing than needed. Sure the process didn’t go the way they said it was going to but the end result was the same. Therefore I dont think any lose of profit should have been awarded.

            November 5, 2026 at 3:24 pm in reply to: 2 (A). What Comes Out in the Wash? #36185
            Caleb Dobson
            Participant

              If an owner fails to evaluate a proposal in accordance with the terms of its solicitation, even if the results would have been the same had it been evaluated correctly, what should be the consequences?

              After lots of contemplating I believe the short answer to this question is that the complaint should be declared valid because the owner breached its legal duty to evaluate bids fairly. However I don’t think E.G. Spence should get their “lost profits” as the error didn’t change the final outcome of the competition.

              November 5, 2026 at 3:07 pm in reply to: 3 (A). Who Bears the Risk of Known Dangers? #36182
              Caleb Dobson
              Participant

                I agree completely April, both parties knew the risks involved, again I do think this falls more on Vasco since he was the expert. But both decided to move forward under pressure to complete the job knowing the risks and choosing to continue which resulted in the worst possible outcome.

                November 5, 2026 at 2:58 pm in reply to: 3 (A). Who Bears the Risk of Known Dangers? #36179
                Caleb Dobson
                Participant

                  I agree completely with you Danny, I think the liability should be shared but I tend to think Vasco would have a greater share of the responsibility since he was hired as the expert in welding, he would have know more than anyone else about the dangers and possible outcomes if work continued and he did anyway.

                  November 5, 2026 at 2:51 pm in reply to: 3 (A). Who Bears the Risk of Known Dangers? #36178
                  Caleb Dobson
                  Participant

                    I also agree that the liability should be shared for these reasons but the majority should land on Vasco because he was the expert and continued to try to perform the work under these conditions. The general contractor really wouldn’t know the extent of the possible dangers since he wasn’t the professional welder.

                    November 5, 2026 at 2:49 pm in reply to: 3 (A). Who Bears the Risk of Known Dangers? #36177
                    Caleb Dobson
                    Participant

                      Who do you think was liable? I think Vasco was liable, even though it appears that he did his due diligence by advising the contractor of the dangers he still performed the work. Normally with WHMIS you should refuse to perform the work if it isn’t safe even if you’re told to do so and report it immediately.

                      Should the subcontractor, Vasco, have been held responsible for the fire damage, when he had performed in accordance with the general contractor’s instructions? Yes, as mentioned above he should have refused to perform the work under unsafe working conditions.

                      Should the general contractor have been liable, when Vasco was the expert in welding, and Vasco’s actions were the actual cause of the fire? I think the general contractor should share some of the responsibilities as he advised Vasco to continue and perform the work after being told by the expert that it wasn’t safe.

                      October 28, 2026 at 11:17 am in reply to: 3 (A). Vested Outsourcing #35893
                      Caleb Dobson
                      Participant

                        I also agree Nancy, as you mentioned it might motivate the vendor to upgrade equipment etc which could help both parties. For example adding my plow trucks would make it so they could accomplish more in less time which could lead to additional contracts so they are increasing their ability to make more money and the end user is happy because the jobs are getting done quickly leading to a healthy and happy relationship with the vendor for years to come.

                        October 28, 2026 at 9:11 am in reply to: 3 (A). Vested Outsourcing #35892
                        Caleb Dobson
                        Participant

                          This seems like a very interesting example, basing results on outcomes instead of trips completed. For rural areas companies could try to pick up as many people as possible at the same time, maybe use mini-buses that are wheel chair accessible. There could be a schedule so you could find out when rides (routes) covered your area. Not ideal for the senior population probably but alternately or in combination you could also have an app (or website) set up much like Uber where you could have ride options: Single, ride share, luxury, etc. This way clients could track the drivers and software could be incorporated so the facilities would know who made driver requests and they’d be able to track the route to see how far/close they were. This would take a lot of resources and a lot of time to develop fully though and given our current healthcare situation probably isn’t feasible anytime soon. Just fun to think about the possibilities though.

                          October 28, 2026 at 9:00 am in reply to: 3 (A). Vested Outsourcing #35891
                          Caleb Dobson
                          Participant

                            Danny this is an excellent example and I agree with moving away from the old ways of doing things by imposing penalties for missing KPIs, and lack of service etc. Solely basing everything on price isn’t working anymore however I do think it is important to consider the options that we recently learned about in our in person training in Fredericton. I think in your example including a transition clause into the RFP would be very helpful….it isn’t punishing the vendor for poor service but it creates incentive to maintain good service, KPIs etc because if they don’t the client can exercise the transition clause to move to a vendor to provide the service and the transition cost etc will be on the current vendor to cover.

                            October 28, 2026 at 8:53 am in reply to: 3 (A). Vested Outsourcing #35890
                            Caleb Dobson
                            Participant

                              I agree April, I think food services is a great example. Also interested in the term of the contract, I’m thinking during the term bench marking could have been included so the health authority could have updates on how everything was going and the possibility of adding new delivery options of meal variations again depending on the scores from the patients.

                              October 28, 2026 at 8:46 am in reply to: 3 (A). Vested Outsourcing #35889
                              Caleb Dobson
                              Participant

                                Yes Monique I agree completely the absolute best approach would be combination of both, which in reality it was. I guess I wasn’t clear stating only the option years as incentive. Another important item to consider is that the option years also help Service New Brunswick maintain some control as if service, deliver or other issues arose in the first five years of the contract they wouldn’t have to extended the option years.

                                October 27, 2026 at 9:57 am in reply to: 2 (A). E-COMM 911 Multi-Stage Procurement Process #35830
                                Caleb Dobson
                                Participant

                                  I have little experience with RFI moving forward to a formal procurement process so I appreciate your insight on this Tony. I think with this example it was clear how one process lead to another seemingly one right after the other as the group were in a hurry for a solution, unfortunately I just have personally experience the procurement process moving along that quickly.

                                • Author
                                  Posts
                                Viewing 15 posts - 16 through 30 (of 48 total)
                                ← 1 2 3 4 →

                                Footer

                                The Procurement School

                                250-370-0041
                                hello@theprocurementschool.com

                                The Atrium
                                #301 - 1321 Blanshard Street
                                Victoria, BC V8W 0B6

                                • TRAINING
                                • PSPP
                                • Webinars
                                •  
                                • QUICK LINKS
                                • Home
                                • Contact
                                • Articles
                                • COMPANY
                                • About
                                • FAQ
                                •  
                                Terms & Conditions   Privacy Policy
                                © The Procurement School

                                Copyright © 2026 · Workstation Pro on Genesis Framework · WordPress · Log in